Payback calculator — hand tying vs TEK Tying Tool
tonnes
40,000 tonnes = 18,144,000 ties. By hand, that is about 27,275 person-hours (≈ 273 days with 10 workers). With TEK, 5,633 person-hours (≈ 56 days).
Jobsite parameters
coils / 1,000 t
= 453.6 ties per tonne (at 210 ties/coil)
workers
Used to compute job days and the number of TEK tools.
h / day
$ / h
TEK equipment
$ / tool
TK-660: $1,300. Enter 0 if the tool is loaned or already owned.
Measured data — cost and time per tie
Hand tying Current
Roll length3,622 in
Wire per tie8.5 in
Ties per roll426.1
Roll price$2.55
Time for 17 ties1 min 32 s
Time per tie5.4 s
Wire cost / tie$0.0060
TEK coil With TEK
Coil length1,260 in
Wire per tie6 in
Ties per coil210
varies by country $
Time for 17 ties19 s
Time per tie1.1 s
Wire cost / tie$0.0238
Measured speed (17 ties: 92 s hand vs 19 s TEK)4.8x faster
Field comparison

Manual tying vs. TEK Tying Tool

Watch both methods work on the same rebar assembly. The side-by-side demonstration puts the measured tying-time difference into context.

Competition: Manual vs. TEK Tying Tools — 1:33
Comparison — tying time
Hand tying Current
Person-hours
27,275 h
Job days (tying)
272.8 days
TEK Tying Tool With TEK
Person-hours
5,633 h
Job days (tying)
56.3 days
Result — estimated payback
Estimated total project savings
$356,134
$981,388 → $625,254
36 %
cost reduction
Hand tying cost
Labor$872,809
Tie wire (42,580 rolls)$108,578
Total$981,388
TEK cost
Labor$180,254
Coils (86,400)$432,000
Tools (10)$13,000
Total$625,254
Tying time saved
216.4 days
Faster delivery = building available sooner.
TEK coils to order
86,400 coils
18,144,000 ties ÷ 210 ties/coil. Replaces 42,580 rolls of tie wire.
Tool paid back after
140.9 t
Per tool: about 20 h of use. Saving of $9.2 per tonne.
$ / day
e.g. rental revenue, avoided late penalties, avoided fixed jobsite costs.
Field-measured data. Hand tying: 3,622 in roll at $2.55, 8.5 in per tie, 17 ties in 1 min 32 s. TEK coil: 1,260 in, 6 in per tie, 17 ties in 19 s. Consumption: 2,160 TEK coils per 1,000 t of steel. TEK coil price adjusts by country. Hours are person-hours; job days depend on the number of workers.